Lifecycle
APD review
315d
file → approval
Plan → spud
-102d
approval → drilling
Drilling
111d
spud → TD
TD → EOR
5d
TD → end-of-ops
Full cycle
329d
first APD → EOR
Plan slip
101d
101d late
APDs filed
9
APMs filed
2
plan modifications
APM resubmittals
2
revision cycles
WARs filed
12
weekly activity reports
Final status
ST
41 event(s) · full audit log
| Date | Event | Op code | Status | Source ID |
|---|---|---|---|---|
| 2025-01-09 | APD_FILED | — | — | -26635 |
| 2025-05-01 | APD_REQ_SPUD | — | — | -26635 |
| 2025-06-17 | APD_APPROVED | — | — | -26635 |
| 2025-07-10 | APD_FILED | — | — | -27109 |
| 2025-08-08 | WAR_FIRST | — | 12 | — |
| 2025-08-10 | SPUD | — | — | 608174151600 |
| 2025-08-12 | APM_FILED | INFORM | ST | -257568 |
| 2025-08-12 | APM_WORK_START | INFORM | ST | -257568 |
| 2025-08-14 | APM_APPROVED | INFORM | ST | -257568 |
| 2025-08-14 | APM_RESUB | INFORM | ST | -257568 |
| 2025-08-20 | EOR_FILED | O | DSI | -204719 |
| 2025-09-28 | APD_REQ_SPUD | — | — | -27334 |
| 2025-09-28 | APD_REQ_SPUD | — | — | -27109 |
| 2025-09-28 | APD_REQ_SPUD | — | — | -27350 |
| 2025-09-28 | APD_REQ_SPUD | — | — | -27369 |
| 2025-09-28 | APD_REQ_SPUD | — | — | -27391 |
| 2025-09-28 | APD_REQ_SPUD | — | — | -27312 |
| 2025-09-28 | APD_REQ_SPUD | — | — | -27406 |
| 2025-09-28 | APD_REQ_SPUD | — | — | -27399 |
| 2025-10-09 | APD_APPROVED | — | — | -27109 |
| 2025-10-10 | APD_APPROVED | — | — | -27312 |
| 2025-10-10 | APD_FILED | — | — | -27312 |
| 2025-10-20 | APD_APPROVED | — | — | -27334 |
| 2025-10-20 | APD_FILED | — | — | -27334 |
| 2025-10-27 | APD_FILED | — | — | -27350 |
| 2025-10-31 | APD_APPROVED | — | — | -27350 |
| 2025-11-03 | APD_APPROVED | — | — | -27369 |
| 2025-11-03 | APD_FILED | — | — | -27369 |
| 2025-11-11 | APD_FILED | — | — | -27391 |
| 2025-11-12 | APD_APPROVED | — | — | -27391 |
| 2025-11-17 | APD_APPROVED | — | — | -27399 |
| 2025-11-17 | APD_FILED | — | — | -27399 |
| 2025-11-19 | APD_FILED | — | — | -27406 |
| 2025-11-20 | APD_APPROVED | — | — | -27406 |
| 2025-11-29 | TD_REACHED | — | — | 608174151600 |
| 2025-12-01 | APM_FILED | ABANDON | ST | -258907 |
| 2025-12-01 | APM_WORK_START | ABANDON | ST | -258907 |
| 2025-12-04 | EOR_FILED | A | ST | -205480 |
| 2025-12-06 | WAR_LAST | — | 12 | — |
| 2025-12-09 | APM_APPROVED | ABANDON | ST | -258907 |
| 2025-12-09 | APM_RESUB | ABANDON | ST | -258907 |
Drilling-permit history (9)
| Status date | Permit type | Well type | WD (ft) | Rig | Operator at filing |
|---|---|---|---|---|---|
| 2025-11-20 | REVISED NEW WELL | E | 3,526 | T.O. DEEPWATER ATLAS | Beacon Growthco Operating Company, L.L.C. |
| 2025-11-17 | REVISED NEW WELL | E | 3,526 | T.O. DEEPWATER ATLAS | Beacon Growthco Operating Company, L.L.C. |
| 2025-11-12 | REVISED NEW WELL | E | 3,526 | T.O. DEEPWATER ATLAS | Beacon Growthco Operating Company, L.L.C. |
| 2025-11-03 | REVISED NEW WELL | E | 3,526 | T.O. DEEPWATER ATLAS | Beacon Growthco Operating Company, L.L.C. |
| 2025-10-31 | REVISED NEW WELL | E | 3,526 | T.O. DEEPWATER ATLAS | Beacon Growthco Operating Company, L.L.C. |
| 2025-10-20 | REVISED NEW WELL | E | 3,526 | T.O. DEEPWATER ATLAS | Beacon Growthco Operating Company, L.L.C. |
| 2025-10-10 | REVISED NEW WELL | E | 3,526 | T.O. DEEPWATER ATLAS | Beacon Growthco Operating Company, L.L.C. |
| 2025-10-09 | REVISED NEW WELL | E | 3,526 | T.O. DEEPWATER ATLAS | Beacon Growthco Operating Company, L.L.C. |
| 2025-06-17 | NEW WELL | E | 3,526 | T.O. DEEPWATER ATLAS | BOE Exploration & Production LLC |